Location Williams Drive from FM 3405 to D.B. Wood Road.
Description The design by KBR includes transitioning from a two-lane roadway to a four-lane roadway with a center two way left turn lane, grading, drainage improvements, asphalt paving, signage, signalization, and striping. This section has been removed from the State Highway System.
Status Construction began March 2009 and is expected to be completed by Fall 2010. 