CR 119

Location Proposed roadway extension for CR 119/Ed Schmidt Boulevard from Limmer Loop to Chandler Road in Hutto, Texas.
Description The project will consist of constructing two lanes of a future four-lane roadway with shoulders and a traffic signal at CR 119 and Limmer Loop. The right-of-way footprint will consider the ultimate typical section. 
Status Final design of the interim two-lane roadway with shoulders is underway by Stantec Consulting Services, Inc. (formerly Bury).  ROW acquisition has been completed and utility relocation coordination is underway. An inter-local agreement with the City of Hutto was approved at the 5/16/17 Commissioners Court meeting. A traffic analysis at CR 119 and Limmer Loop is complete, and a traffic signal has been warranted. Construction is anticipated to begin in late 2017.
Contact Email roads@wilco.org or phone 512-846-1190